 TENTATIVE FACILITIES PLANNING TIMELINE  (updated 5-14-2018)

 

MAY 9, 2018                    RFP’s issued to Architects & Construction Managers

MAY 16, 2018                  AGSD Site Visit with Scott Millward, Facilities Director

MAY 25, 2018                  Architect RFP Questions Due 

MAY 30, 2018                  Construction Manager RFP's Due 

MAY 31, 2018                   Architect RFP Due - Step 1 

JUNE 4-6, 2018                Step 1 Architect Screenings

JUNE 6, 2018                    Screening Committee Recommends Finalist Shortlist

JUNE 14, 2018                  Board Interviews Construction Managers

JUNE 26, 2018                  Special Board Meeting:  Architect 2nd Interviews & Construction Manager
                                            Contract

JULY 9, 2018                      Special Board Meeting:  Architect Contract

Architect RFP